Site Survey

Quick Definition

A site survey is the systematic assessment of a proposed solar installation site, evaluating roof or land condition, electrical infrastructure, shading, structural load capacity, accessibility and regulatory feasibility. It is the foundation for accurate design and quotation.

Quick Facts

Term
Site Survey
Category
Installation
Industry
Solar Installation
Primary Use
Pre-installation site assessment
Common Users
EPCs, installers, sales teams
Standards
MNRE design guidelines
Related Technologies
Drone survey, structural analysis, electrical assessment

What is a site survey

A site survey is the systematic on-site assessment of a proposed solar installation location. It evaluates roof or ground area, structural capacity, shading patterns, electrical infrastructure, sanctioned load, accessibility, regulatory feasibility and customer requirements. For complex commercial or ground-mount projects, EPCs often bring in professional site survey and land feasibility services to validate technical viability before a contract is signed. The survey produces a feasibility report that forms the basis for system design, quotation and DISCOM application.

For Indian solar installations, the site survey is the critical first step in any project. PM Surya Ghar residential applications, C&I rooftop tenders and utility-scale plant development all begin with a site survey. Survey quality directly affects project economics, regulatory compliance and customer satisfaction.

Why site surveys matter

Accurate design. Without measured data, design assumptions are guesses.

Cost estimation. Material quantities depend on actual dimensions and roof types.

Risk identification. Structural, electrical and shading risks emerge during survey.

DISCOM application. Net metering application requires site-specific data.

Customer expectation setting. Honest survey prevents overpromise on yield.

Compliance verification. CEIG and DISCOM rules vary by site type.

Site survey components

What a site survey collects
ComponentInformation collected
Site locationAddress, GPS coordinates
Roof or land areaDimensions, total available area
Roof typeRCC, metal sheet, tile, asbestos
Structural capacityBay layout, beam spacing, age, load capability for the mounting structure
ShadingTrees, buildings, parapets, water tanks
OrientationTrue azimuth and tilt of available area
Electrical infrastructureMains panel, sanctioned load, phase configuration
Connection distanceDistance from array to inverter location
EarthingExisting earth pits, soil type
PhotographsRoof, mains panel, surroundings, electricity bill
Customer requirementsBackup needs, expansion plans, budget

Technical deep dive

Residential rooftop survey checklist

  1. Verify ownership and society NOC.
  2. Measure usable roof area.
  3. Photograph all four orientations and the centre.
  4. Identify shading from sun path 9 am to 4 pm.
  5. Check roof material and age.
  6. Inspect mains electrical panel.
  7. Record sanctioned load from bill.
  8. Locate suitable inverter wall (shaded, ventilated).
  9. Plan AC cable route to mains panel.
  10. Identify earth pit location.

Drone survey (large rooftops and ground-mount)

For large or complex sites, many EPCs supplement the manual walkthrough with a satellite roof measurement pass or a dedicated 3D pre-design site modeling service that combines drone capture with CAD-ready outputs.

Drone survey stages and what each produces
StageOutput
Flight planningSurvey area boundary, altitude, overlap
Image captureRGB photos at 80 percent overlap
ProcessingOrthomosaic, 3D model, contour map
AnalysisRoof areas, shading obstructions, fault lines

Structural load check

Roof load assessment for residential RCC:

  • Panel + structure weight (dead load): 12 to 15 kg/m², about 0.12 to 0.15 kN/m²
  • Design wind pressure (illustrative, from IS 875 Part 3 for the site’s wind zone and height): 1.2 to 1.5 kN/m², about 122 to 153 kg-force/m² (1 kN/m² ≈ 102 kg-force/m²)
  • Wind acts mainly as uplift, so it is checked against the structure’s anchoring and ballast, not added to the dead load

Typical RCC residential roofs comfortably handle this. Old houses, metal sheet roofs and asbestos roofs need structural engineering review.

Electrical infrastructure check

Electrical checks during a site survey
ParameterWhat to verify
Sanctioned loadFrom electricity bill, in kW or kVA
Phase configurationSingle-phase 230 V or three-phase 415 V
Mains panel capacityAdequate breaker for solar AC
Earth pitExisting or to be created
Cable routeDistance from inverter to mains
Roof to inverterDC cable route distance

Real-world applications

Residential PM Surya Ghar pre-application.

C&I rooftop tender pre-bid survey, typically conducted by the turnkey EPC contractor.

Utility-scale solar park site selection.

Carport solar feasibility.

Floating solar reservoir assessment.

PM-KUSUM agri solar pump survey.

Common site survey problems

Inadequate shading documentation leading to underperformance.

Missing structural review on metal sheet or old RCC roofs.

Underestimated cable routing distance.

Ignoring future obstructions (planned construction nearby).

Skipping CEIG-relevant safety distances.

Missing tenancy or society NOC documentation.

Best practices

Use standardised survey checklists.

Photograph every relevant feature.

Capture GPS coordinates for accurate sun-path modelling.

Conduct shading observation at 2 to 3 hour intervals if possible.

Verify electrical bill and sanctioned load.

Document customer requirements explicitly.

Provide a written feasibility report.

Use drone surveys for large or complex sites.

Comparison: residential vs C&I vs utility surveys

Residential, C&I and utility site surveys compared
AspectResidentialC&IUtility
Duration1 to 4 hours4 to 8 hours1 to 5 days
ToolsTape, camera, multimeterDrone, structuralDrone, geotechnical, met-mast
OutputFeasibility reportDetailed design packageBankable feasibility
CostFree in PM Surya GharFree to ₹50,000₹2 to ₹20 lakh

Indian market context

PM Surya Ghar workflow includes installer site survey before DISCOM approval.

C&I rooftop tenders include site survey for capacity confirmation.

SECI utility tenders require detailed bankable feasibility including geotechnical, hydrological and resource assessment.

Drone surveys are increasingly common for C&I rooftops and ground-mount plants.

State agencies under PM-KUSUM conduct site surveys for agricultural solar.

Standards and certifications

Guidelines and procedures that feed a site survey
StandardScope
MNRE Design GuidelinesIndian solar PV design
IEC 61724Performance monitoring (referenced for resource assessment)
BIS structural codesRoof load assessment
State CEIG proceduresDrawing approval input
PM Surya Ghar portalResidential workflow

Common mistakes

Skipping winter shading observation.

Ignoring society NOC requirements.

Underestimating cable route.

Missing future construction risk.

Not photographing existing earthing.

Skipping structural review on metal sheet roofs.

Key takeaways

Site survey is the foundation of any solar installation. It evaluates roof or land area, shading, structural capacity, electrical infrastructure and regulatory feasibility. Indian residential surveys take 1 to 4 hours; C&I 4 to 8 hours; utility 1 to 5 days. Quality of survey directly determines design accuracy, cost predictability and customer satisfaction.

Need professional site survey for solar?

Qbits’ public material does not describe a standard site-survey service, its coverage area, deliverables or fee. Contact Qbits to ask whether a survey is available for the project location and to get its scope, responsible party, price and deliverables in writing. Otherwise, appoint a qualified project designer or installer.

Further reading

For how Site Survey plays out in real projects, these guides go deeper:

Sources

  • MNRE Design Guidelines for Solar PV Plants.
  • IEC 61724-1, Performance monitoring.
  • IS 875, Wind load on structures.
  • BIS structural codes.
  • PM Surya Ghar Muft Bijli Yojana operational guidelines.
  • State CEIG procedures and drawings checklists.
  • PVsyst documentation on site assessment.
  • Drone industry guidelines for solar survey.
  • IEA PVPS Task 13 publications.
FAQ

Frequently Asked Questions

What is a site survey in simple words?
An on-site visit to check whether solar can be installed at your location, how big a system will fit, and what it will cost. Done before any design or quotation.
What does a site survey cover?
Roof condition and area, structural capacity, shading, electrical infrastructure, sanctioned load, distance to inverter location, earthing arrangement, regulatory feasibility.
How long does a site survey take?
1 to 4 hours for residential. 4 to 8 hours for C&I. 1 to 5 days for utility-scale.
What is included in a residential rooftop survey?
Available roof area, shading from nearby buildings and trees, water tank position, parapet height, roof material and age, electrical bill, DISCOM connection details.
What is structural load assessment?
Engineering check of whether the roof can support the additional weight of panels, structure and wind/snow loads.
Do I need a structural engineer?
For residential RCC rooftops: usually not required, basic visual inspection sufficient. For metal sheet, asbestos or old roofs: structural review needed.
What documents are collected during survey?
Latest electricity bills, property ownership documents, sanctioned load proof, society NOC if applicable, identity proof.
Can drones be used for site survey?
Yes. Drone surveys provide aerial photographs, 3D models and shading analysis especially for large rooftops and ground-mount sites.
What is irradiance assessment during survey?
Recording site location for off-the-shelf irradiance data lookup. Long-term resource assessment uses NIWE, Solargis or NSRDB.
Are site surveys paid?
Often free for prospective customers as part of sales process. Some EPCs charge a refundable fee.
Can I survey my own site?
You can assess basic parameters (roof area, sun exposure) but professional structural and electrical assessment is recommended.
What if my roof cannot take the load?
Reinforcement may be possible. Alternative: carport, ground-mount or RESCO arrangement on neighbouring property.
Do I need DISCOM survey separately?
Yes, for net metering. DISCOM conducts a technical feasibility study after application submission.
What is a feasibility report?
Summary document from site survey including roof analysis, shading, recommended capacity, expected generation and indicative cost.
Can a survey be done remotely?
Partially. Google Earth and satellite imagery support initial assessment. Final design requires on-site visit.
Nirav Dhanani
Written by
Nirav Dhanani · CEO

Co-founder & CEO driving Qbits Energy's product strategy and growth across India.

Apply this definition to an exact inverter design

Check the relevant model datasheet and installation manual. A definition or calculation alone does not confirm equipment compatibility or grid approval.