How to Evaluate Solar EPC Bids: A Procurement Checklist

Normalise scope and BOQ, test design and generation assumptions, allocate responsibilities, compare commercial terms, and score only compliant solar EPC bids.

Keyur Rakholiya
Keyur Rakholiya CTO
March 22, 2026 Updated October 14, 2026 10 min read

To understand how to evaluate solar EPC bids, normalise every bidder against one requirement, bill of quantities, design basis, responsibility matrix, programme, acceptance plan, O&M scope, and commercial template. Apply technical pass/fail gates before weighted scoring. Compare price only after omissions, exclusions, assumptions, risk transfers, and unresolved deviations are visible.

This checklist is for project procurement teams and qualified technical, commercial, financial, legal, tax, safety, and grid reviewers. It does not provide a universal score weighting, price, yield, warranty, or contract term.

What should be issued to every EPC bidder?

Issue one controlled request with site data, objectives, capacity definitions, surveys, utility information, design criteria, approved makes process, BOQ format, interfaces, exclusions, programme, safety, tests, handover, O&M, commercial schedules, and response instructions. Require bidders to list deviations and data gaps instead of silently creating different assumptions.

The bid package should state:

  • project site, access, land or roof rights and available surveys;
  • load, connection, metering, export, grid and operating requirements;
  • whether capacity means module DC kWp, inverter AC kW, export limit, battery power or energy;
  • design life or analysis horizon only where the owner has approved it;
  • minimum design, structural, electrical, safety and documentation requirements;
  • owner-supplied work, third-party interfaces and authority responsibilities;
  • BOQ units and pricing schedule;
  • programme milestones and dependency register;
  • commissioning, performance and handover requirements; and
  • contract, payment, security, insurance, liability and change schedules for review.

Record clarifications centrally and issue the same answer to every bidder where procurement rules require equal information.

How should scope and BOQ be normalised?

Create a master BOQ and responsibility matrix, then map every bidder’s quantity, specification, inclusion, exclusion, unit rate, assumption, and evidence to it. Do not compare lump sums until missing scope, owner-supplied work, provisional quantities, optional items, taxes, freight, application costs, and interface responsibilities have been reconciled.

Bid normalisation matrix, mapping each bidder to the master BOQ by work package
Work packageBid ABid BOwner requirementStatus
Survey and engineeringPass, gap or deviation
Modules, inverters and controlsPass, gap or deviation
Structure and civil workPass, gap or deviation
DC and AC balance of systemPass, gap or deviation
Protection, earthing and lightningPass, gap or deviation
Metering, communication and monitoringPass, gap or deviation
Grid, authority and customer interfacesPass, gap or deviation
Testing, commissioning and handoverPass, gap or deviation
O&M, spares and trainingPass, gap or deviation

Track quantities by unit and basis. A bidder can be cheaper because the structure tonnage, cable length, protection, access, grid work, documentation, or O&M scope differs, not because execution is more efficient.

How should technical compliance be checked?

Use pass/fail gates for mandatory site, structural, array, inverter, protection, grid, environmental, safety, monitoring, and documentation requirements. Verify exact models and calculations against current documents. A commercial score or preferred brand cannot offset an unresolved safety, compatibility, authority, or mandatory-performance failure.

Review at least:

  1. site survey, layout, shading and access basis;
  2. structural loads, interfaces, corrosion environment and waterproofing;
  3. module string voltage, current, temperature and MPPT allocation;
  4. inverter AC rating, phase, grid interface, environment and communications;
  5. cable sizing, routing, isolation, protection, earthing and coordination;
  6. transformer, switchgear, meter, CT, plant controller and utility interface where applicable;
  7. monitoring points, data ownership, retention, alarms and cyber access;
  8. construction method, permits, safety plan and quality records; and
  9. exact evidence for every proposed deviation or alternative.

Use the EPC inverter-selection scorecard for the hardware sub-review and the string-sizing guide for the DC calculation record. Neither replaces whole-project engineering approval.

How should generation assumptions be compared?

Put every energy model on the same weather, layout, equipment, capacity, shading, loss, availability, curtailment, grid-outage, degradation, and uncertainty basis. Require monthly outputs and the model file or reproducible report. Separate an engineering estimate from a contractual guarantee, and define how any guaranteed result will be measured and adjusted.

Generation review table:

Generation assumption comparison, with the common basis every bidder’s energy model should share
Input or lossCommon basisBidder evidenceDeviation or sensitivity
Weather and irradiationSource, years and processing
Layout and shadingApproved geometry and method
EquipmentExact module and inverter models
CapacityDC, AC and ratio definitions
LossesNamed categories without double counting
Availability and outagesResponsibility and exclusions
Curtailment or export controlControl and grid assumption
DegradationSource and application method
UncertaintyDeclared range or sensitivity

Do not compare two performance ratio or annual-yield numbers until the boundary, formula, period, data quality, correction method, exclusions, and remedy are the same.

How should programme, commissioning and handover be reviewed?

Review the programme as a dependency network, not only a completion date. Identify surveys, design approvals, procurement, permits, access, shutdowns, civil works, grid and meter activities, installation, testing, defect correction, authority inspection, energisation, performance verification, training, as-built records, and handover, with an accountable party for each dependency.

Ask each bidder to provide:

  • logic-linked programme and critical dependencies;
  • long-lead equipment and substitution control;
  • owner, utility and authority action register;
  • inspection and test plan with hold points;
  • pre-commissioning, energisation and functional test procedures;
  • acceptance criteria and defect-closeout process;
  • serial-number, setting, firmware and test-result register;
  • as-built drawings, manuals, warranties and training; and
  • incomplete-work and punch-list treatment at commercial completion.

The solar inverter commissioning guide explains the inverter evidence subset. An app screenshot or energy reading does not close whole-project commissioning.

How should O&M and responsibility boundaries be compared?

Define who observes, inspects, tests, cleans, responds, diagnoses, repairs, replaces, reports, escalates, and coordinates warranties for every asset and interface. Compare triggers, competence, access, spares, response process, exclusions, parts, labour, travel, monitoring, reports, term, renewal, termination, and the transition from EPC defects to O&M obligations.

Use a responsibility matrix for:

Responsibility matrix for EPC, OEM, O&M, owner and utility by event
EventEPCOEMO&M providerOwnerUtility or third party
Design error
Product defect
Workmanship defect
Grid event or curtailment
Monitoring loss
Routine maintenance
Warranty claim and logistics
Emergency or safety event

The bid should not use comprehensive O&M without a task, evidence and exclusion schedule. Warranty duration also does not explain labour, freight, site attendance, replacement, or lost-generation treatment.

How should commercial bids be normalised?

Reconcile price after technical and scope normalisation. Identify taxes, duties, escalation, freight, insurance, securities, retention, payment timing, provisional sums, owner costs, finance, working capital, change rules, delay treatment, warranties, liabilities, exclusions, options, O&M, spares, replacements, and end-of-term obligations before comparing the evaluated commercial position.

Use:

Do not display a result if gaps lack quantities or approved valuation rules. Mark the comparison incomplete. Keep risk assessment separate from arithmetic where probability or consequence evidence is unavailable.

For inverter lifecycle scope, the inverter TCO guide provides an input-led worksheet. Obtain legal, tax, insurance and finance review for the project contract.

How should a weighted bid worksheet be built?

Build weights from the owner’s approved objectives and risk, make the total equal 100, define each score before opening commercial bids where governance requires it, and attach evidence to every score. Mandatory gates stay outside the weighting. Sensitivity-test the result so small subjective changes do not silently determine the award.

Worksheet fields:

Weighted bid worksheet fields, with approved weight, score definition and evidence per category
CategoryApproved weightScore definitionBidder evidenceWeighted result
Technical compliance beyond gates
Design and generation quality
Delivery and commissioning
Quality, safety and documentation
O&M, warranty and service
Commercial and contractual position
Organisation and references

For each category, calculate the weighted result above, then sum category results only after the score definitions and units are checked. Do not award points for unsupported claims or let the same benefit score in multiple categories.

What should happen before contract award?

Before award, close mandatory deviations, validate references and capability, reconcile scope and price, review design and generation assumptions, confirm authority interfaces, complete legal and financial review, document score sensitivity, and carry every accepted clarification into the final contract. The award recommendation should list conditions, open risks, owners, and required pre-start evidence.

Final checks:

  1. Verify legal entity, financial and delivery capability using approved due diligence.
  2. Contact relevant references with project-specific questions and consent.
  3. Confirm exact equipment, supply route and approved substitutions.
  4. Freeze the requirement, BOQ, responsibility matrix and deviation register.
  5. Reconcile price, tax, payment, security, O&M and option schedules.
  6. Confirm programme dependencies and authority responsibilities.
  7. Complete technical, safety, legal, tax, insurance and finance approvals.
  8. Issue a reasoned recommendation and retain the evaluation evidence.

Use the datasheet library or contact Qbits for an exact-model inverter review inside the wider procurement process. Set your own scoring weights with project procurement and engineering before applying this framework to live bids.

Sources checked 23 September 2026: current Qbits inverter-selection, string-sizing, commissioning and TCO guides plus current public Qbits datasheets. No bid result, weight, price, yield, service level or contract outcome is claimed.

Qbits models

Specs below come from each model's datasheet. Confirm the exact model and current written terms with Qbits before you buy.

Browse all c&i solution →

FAQ

Frequently Asked Questions

How should solar EPC bids be evaluated?
First normalise the requirement, BOQ, capacity definitions, design basis, exclusions, responsibilities, programme, tests, handover, O&M, and commercial assumptions. Reject or hold noncompliant bids before scoring. Then apply approved weights to supported evidence, run price and risk reconciliation, complete due diligence, and document the award conditions.
What belongs in a solar EPC bid comparison sheet?
Include bidder and legal entity, technical deviations, module and inverter models, quantities, DC and AC capacities, layout, yield assumptions, structure, electrical balance of system, grid and metering scope, civil works, safety, programme, testing, documentation, warranties, O&M, exclusions, taxes, payment, securities, liability, change control, and price.
Should the lowest solar EPC bid win?
Not automatically. A lower number may omit required work, use different capacity definitions, rely on unsupported generation, transfer risk, defer authority costs, weaken testing, or exclude O&M and handover. Compare compliant, normalised scope and commercial risk before price, then record why the selected bid is acceptable.
How should generation guarantees be compared?
Require the same weather basis, site layout, shading, equipment, DC and AC capacities, loss categories, availability, degradation, curtailment, grid outage, measurement boundary, uncertainty, exclusions, test period, correction method, data source, remedy, and responsibility. A single annual yield or performance ratio is not comparable without its model and contract definition.
How does EPC bid evaluation differ from inverter selection?
EPC evaluation covers the complete project, including survey, design, equipment, civil and electrical work, approvals, grid interface, programme, safety, commissioning, handover, O&M, commercial terms, and risk. Inverter selection is one technical procurement decision inside that wider scope and should not determine the whole-project award by itself.
Keyur Rakholiya
Written by

Keyur Rakholiya CTO, Qbits Energy

Listed by Qbits as its CTO. Current role, technical responsibilities and credentials require confirmation by the company owner.

Related Reading
Solar Software 9 min

Solar Takeoff Software: Auto-BOQ Guide 2026

Solar takeoff software pulls quantities straight from the design canvas. Compare SurgePV, Aurora, HelioScope, and OpenSolar on auto-takeoff and export.

EPC 15 min

How to Read Solar Inverter Datasheets

Turn an exact-model inverter datasheet into checked design inputs, BOQ line items, a tender compliance matrix, and a traceable technical submission.

Get Started

Preparing an inverter shortlist or RFQ?

Send the required model or capacity, quantity, grid connection, project location and delivery date. Request the exact-model documents and written supply terms.