Solar Inverter Selection Scorecard for EPCs

A documented EPC scorecard for screening solar inverters against site limits, array design, grid requirements, service terms and lifecycle cost.

Nirav Dhanani
Nirav Dhanani CEO
March 16, 2026 Updated October 14, 2026 11 min read

A useful solar inverter selection scorecard starts with pass-or-fail engineering limits, then compares the surviving models on documented commercial and service criteria. This order prevents an attractive price, warranty headline or feature list from hiding a mismatch in voltage, current, phase, environment or grid requirements.

The framework below is for EPC procurement teams. It does not replace the project electrical design, the applicable DISCOM process, or an engineer’s review of the exact equipment and installation.

What should an EPC define before comparing inverters?

Define the project requirements before asking suppliers to score themselves. Record the array design envelope, AC connection, environmental conditions, operating objective, monitoring obligations, service expectations and commercial evaluation period. Without this baseline, every bidder can appear compliant by answering a different version of the project.

Create a project requirement sheet with these inputs:

Project requirement sheet: inputs to record and the evidence used to set them
Requirement groupProject input to recordEvidence used to set it
PV arrayModule model, string layout, voltage and current envelopeCurrent module data and design calculations
AC connectionRated output, phase, voltage and utility requirementsApproved single-line diagram and connection documents
SiteAmbient conditions, enclosure location, altitude and exposureSite survey and project specification
OperationExport, self-consumption, backup or plant-control objectiveClient brief and approved control philosophy
MonitoringSignals, communications, portal access and data handoverO&M and client reporting requirements
SupportResponse path, spares, training and escalationProcurement and O&M plan
CommercialQuote scope, warranty, service and evaluation periodTender and contract documents

Which criteria should be pass or fail?

Any criterion that can make the design unsafe, non-compliant or inoperable belongs in the pass-or-fail screen. Typical gates cover DC voltage and current, MPPT compatibility, AC output and phase, environmental limits, required grid evidence, protection interfaces and approved battery pairing where storage is included.

Use the exact proposed model, not a family name. Check at least:

The datasheet-reading guide explains how to separate maximum DC voltage, MPPT range and start-up voltage. Use the string-sizing calculator only as an initial screen, then verify the design against current module and inverter documents.

How should an EPC compare models that pass?

Score only the compliant models, using criteria and weights agreed before commercial bids are opened. A practical matrix can cover design fit, evidence quality, monitoring, service, warranty, supply execution and total cost. Add notes and document references beside every score so another reviewer can reproduce the decision.

Use a scale such as 0 = no acceptable evidence through 5 = fully meets the documented requirement. The scale is a procurement convention, not a product-performance claim. Define what each score means for each criterion before evaluation.

Scored criteria, what to compare and the evidence to retain
Scored criterionWhat to compareEvidence to retain
Design fitMargin to project limits and layout flexibilityDesign sheet and exact model datasheet
Evidence qualityScope, revision and model matchCertificate, report or registry record
MonitoringRequired signals, hardware, access and exportManual, demo record and quoted accessories
CommissioningTools, instructions and acceptance supportManual and support commitment
WarrantyRemedy, exclusions, costs and claim stepsControlling written policy
ServiceEscalation, diagnosis, spares and responsibilitiesService schedule or contract
SupplyLead time, substitutions and version controlQuote and purchase terms
Ownership costAcquisition, service, downtime and replacement inputsTCO worksheet and supporting quotes

Do not award points for an adjective such as “smart,” “premium” or “AI-powered.” Score the observable function the project needs, the evidence that it exists, and who must provide the hardware or subscription.

How should efficiency and thermal behaviour be assessed?

Compare efficiency and thermal behaviour under stated conditions, not through one headline percentage. Record the efficiency metric, test basis, load range and any temperature or altitude derating that affects the site. Model expected energy with consistent assumptions if the difference matters to the procurement decision.

Maximum efficiency is not annual yield. Likewise, an operating temperature range does not prove that full output is available throughout that range. Request the applicable derating curve or manual and check whether the proposed mounting conditions preserve ventilation and required clearances.

If an energy-value comparison is included, keep the model inputs, loss assumptions and tariff basis in the decision file. Do not convert a datasheet difference into a lifetime saving without a reviewed energy model.

How should enclosure and site conditions be scored?

Match the documented enclosure and environmental limits to the surveyed installation, rather than declaring one IP rating universally sufficient. Rain exposure, dust, salt, direct sun, flooding risk, ventilation, altitude and maintenance access can change the mounting decision even when two products carry the same headline enclosure rating.

The IP65 versus IP66 guide explains what an ingress code does and does not establish. The EPC should also check the manual’s mounting orientation, clearances, connector requirements and any restrictions for corrosive environments. An IP code does not replace those installation instructions.

What should be checked in warranty and service terms?

Read the controlling warranty and service documents for the exact model. Compare when coverage starts, registration requirements, covered faults, remedy, exclusions, diagnostic steps and responsibility for labour, removal, transport and reinstallation. A duration shown in a brochure cannot answer those questions on its own.

The solar inverter warranty guide provides a document checklist. Retain the policy version with the purchase file instead of relying on a web-page summary that may later change.

How should monitoring and support be evaluated?

Test the monitoring and support workflow against the O&M team’s actual job. Confirm commissioning access, user roles, alarm detail, data export, connectivity hardware, subscription terms, firmware responsibilities and the route for technical escalation. A feature list is not a completed workflow test.

Ask the supplier to demonstrate a normal commissioning sequence and a fault escalation. Record whether extra gateways, SIMs, licences or mobile permissions are needed. Check what the client receives at handover and how access transfers if the original EPC no longer maintains the plant.

Support can be scored only from defined evidence. Named contacts, documented hours, escalation steps, training material and spare-parts commitments are more useful than an unqualified promise of “fast service.”

How should total cost affect inverter selection?

Compare total cost using the same scope, period and assumptions for every compliant model. Include installed acquisition cost, required accessories, commissioning, planned service, monitoring fees, expected downtime exposure, warranty responsibilities and replacement scenarios. Keep uncertain inputs visible instead of disguising them inside one confident total.

The inverter TCO worksheet provides the input structure. Run sensitivity cases for the inputs that can change the decision, such as service visits, downtime value, replacement timing or discount rate. A lower purchase price should win only if the comparable evidence supports the lower ownership cost or the client has explicitly prioritised capital cost.

A solar inverter selection scorecard template

Complete the pass-or-fail section first. Reject or resolve every failure before weighted scoring.

Technical gate

Technical gate: pass-or-fail template for each candidate model
GateRequired value or documentCandidate resultEvidence referencePass/fail
Exact model and revision
Maximum DC voltage
MPPT voltage range
Input current limits
AC rating and phase
Environmental limits
Grid and project evidence
Storage compatibility, if applicable

Weighted comparison

Weighted comparison template for models that pass the technical gate
CriterionProject weightCandidate scoreWeighted resultEvidence and notes
Design fit
Evidence quality
Monitoring and commissioning
Warranty and service
Supply execution
Total cost of ownership

Have engineering approve the technical gate, O&M review monitoring and support, and procurement confirm the commercial comparison. Record the chosen model, rejected alternatives, open conditions and approvers in the decision note.

What should happen before a purchase order is released?

Before release, match the selected model and every promised accessory to the final design, quote and evidence file. Resolve qualifications, approve substitutions formally, attach the controlling warranty and define commissioning and handover records. The purchase order should not rely on a scorecard entry that the contract does not preserve.

The final file should include the approved single-line diagram, array calculations, exact SKU, current datasheet and manual, required compliance evidence, monitoring scope, warranty, service terms, delivery conditions and acceptance tests. Download current Qbits datasheets or request a model-specific technical review before procurement.

Sources checked 23 September 2026: the current Qbits datasheet library, Qbits product inventory and the linked Qbits technical guides. Product, certificate, warranty and support statements must be reconfirmed for the exact quoted model and project. Engineering, procurement and contract owners should approve the final scorecard before purchase.

Qbits models

Specs below come from each model's datasheet. Confirm the exact model and current written terms with Qbits before you buy.

Browse all on-grid inverters →

FAQ

Frequently Asked Questions

Should an EPC score every inverter before checking technical limits?
No. Treat electrical, environmental, grid and project requirements as pass-or-fail gates first. Score only the models that satisfy every mandatory limit. A high commercial score cannot compensate for an incompatible MPPT window, insufficient current capacity, unsuitable output phase or missing project evidence.
Is the highest-efficiency inverter always the best selection?
No. Compare efficiency under documented conditions, but also check array compatibility, temperature behaviour, grid requirements, service terms and the cost of operating the exact project. A headline maximum-efficiency figure does not establish annual energy or project suitability by itself.
What evidence should an EPC request from an inverter supplier?
Request the current model datasheet and manual, model-specific certificates or registrations required for the project, written warranty and service terms, monitoring documentation, accessory list and commercial quote. Record document versions so the approved evidence can be matched to delivered equipment.
How should warranty be scored?
Score the written remedy, exclusions, registration, labour and transport responsibilities, claim route and service capacity, not the headline duration alone. Apply the same questions to every bidder and mark any missing term as unverified until the supplier provides the controlling document.
Can one scorecard be reused for every project?
Reuse the structure, not the thresholds or weights. Each project's array, grid connection, environment, monitoring obligations, client priorities and contract terms should set its own pass-or-fail limits and scoring weights before supplier responses are opened.
Nirav Dhanani
Written by

Nirav Dhanani CEO, Qbits Energy

Co-founder & CEO driving Qbits Energy's product strategy and growth across India.

Related Reading
Buying Guide 9 min

Why Qbits Inverter Prices Are Quote-Based

Why Qbits publishes inverter specifications but not a public price list, what changes a project quote, and how EPC buyers can request comparable written pricing.

Get Started

Compare inverters for your application

Shortlist the right inverter type and phase, then request current documents and an exact-model quotation.