Gujarat households searching for the Surya Gujarat scheme want one number: how much subsidy they will get. The honest answer is that the number you can rely on today comes from the central scheme, not from the state programme that gave this search its volume.
Surya Gujarat, formally the Surya Urja Rooftop Yojana, is Gujarat’s own rooftop solar programme. It runs through Gujarat Urja Vikas Nigam Limited (GUVNL) and its distribution companies, and it predates the national scheme. Much of the material still circulating about it, including the per-kW state top-up figure repeated across solar websites, traces back to orders issued years ago.
This guide separates three things that get blended together. First, what Surya Gujarat is and where it sits now. Second, the central PM Surya Ghar assistance that actually pays out, with slab amounts and the order behind them. Third, the Gujarat layer: your licensee, the state metering rules, the vendor requirement, the documents, and the timing written into the regulations. Every figure carries its issuing body and year, and where a widely repeated number has no current order behind it, this guide says so.
Short version. Surya Gujarat is Gujarat’s state rooftop solar programme, run by GUVNL through UGVCL, MGVCL, PGVCL, DGVCL and Torrent Power. In 2026 the subsidy that actually disburses is central: ₹30,000 per kWp for the first 2 kW and ₹18,000 for the third, capped at ₹78,000, per MNRE (2024). Any Gujarat state top-up must come through the National Portal, backed by a current order.
Is the SURYA Gujarat state top-up open right now?
No verified state top-up is open for new residential applications as of October 2026. Here is what that rests on.
- The SURYA Gujarat portal (GUVNL) still shows its last new-application window as 23 November 2023 to 8 December 2023, and its discovered rates are labelled 2020-21.
- We searched for a Gujarat government, GEDA or GUVNL order announcing a current per-kW residential top-up and found none. Installer blogs quote different figures (₹10,000 per kW, ₹15,000 per kW, or flat sums for 1 to 3 kW), and none of them cites a notification.
- MNRE’s guidelines (clause 5(i)) require any state component to be disbursed through the National Portal, so a real top-up would show up in your application, not only on a quotation.
This position can change if the state issues a new order, so re-check GEDA, GUVNL and your discom before you sign.
What Surya Gujarat actually is
Surya Gujarat is a single-window rooftop photovoltaic portal operated by GUVNL, supported by GIZ and AHAsolar. It handles vendor empanelment, consumer applications and tracking. It is a delivery channel and an empanelment register, not a separate cheque.
The programme left Gujarat with real stock. Gujarat had 8,146.70 MW of grid-connected rooftop solar as on 31 August 2026, the highest of any state, out of a national 32,595.64 MW, according to MNRE (2026). That is almost exactly a quarter of India’s rooftop fleet. Read the heading carefully: it covers all grid-connected rooftop including commercial and industrial, not the scheme alone.
One correction to a common claim. Gujarat leads on cumulative stock, not on the latest year’s additions. Maharashtra added the most rooftop capacity in FY2026 at 2,144 MW against Gujarat’s 1,777 MW, according to JMK Research (2026). Having the most installed is not the same as installing the most now.
Two dates on the portal matter. Its most recent new-application alert covers 23 November 2023 to 8 December 2023, for PGVCL and MGVCL rural tenders plus Torrent Surat urban. Its discovered rates are labelled 2020-21. Both signal a channel in maintenance mode, not an open state window.
Does the state scheme stack on top of PM Surya Ghar?
Stacking is permitted by design, and the mechanism is specified. Clause (i) of the MNRE Operational Guidelines (2024) lets state governments supplement central assistance with an additional residential subsidy. The same clause requires any state component to be disbursed through the National Portal.
That gives you a clean test. A genuine state top-up appears inside your portal application and pays through the same channel. It does not arrive as a line on a sales quotation.
Note also what got absorbed. The Rooftop Solar Phase II Programme, running since 2019, stands subsumed within PM Surya Ghar, and Phase II installations are not covered under the newer scheme, per MNRE (2024). Our PM Surya Ghar guide covers the central scheme end to end.
The subsidy structure, with slabs and dates
The slabs are set in the MNRE Operational Guidelines issued as Order No. 318/17/2024-Grid Connected Rooftop dated 16 March 2024. Rates are per kWp of installed capacity, and the third kW is paid at a lower rate.
| Capacity | Central assistance rate | Gujarat applies |
|---|---|---|
| First 2 kW | ₹30,000 per kWp | Yes |
| Third kW | ₹18,000 per kWp | Yes |
| Above 3 kW | No further assistance for a single household | Yes |
| Special category states | ₹33,000 and ₹19,800 per kWp | No |
| Group housing society common facilities | ₹18,000 per kWp, up to 500 kWp at 3 kWp per house | Yes |
Gujarat is not on the special category list, per MNRE (2024). That list covers Uttarakhand, Himachal Pradesh, Jammu and Kashmir, Ladakh, the North East including Sikkim, and the island union territories. A Gujarat household uses the standard rates.
One detail decides which year’s rates apply.
For other states side by side, see our state-wise solar subsidy comparison.
Who is eligible, and who is excluded
Eligible installations are grid-connected residential systems on a roof, terrace, balcony or elevated structure, including building-integrated photovoltaics, per the MNRE Operational Guidelines (2024). Group and virtual net metering installations qualify if the discom approves the metering arrangement.
The exclusions are specific rather than general:
- Elevated structures below 8 feet of ground clearance at the lowest point.
- Non-DCR modules in any form. The Domestic Content Requirement means domestically manufactured modules using domestically manufactured cells.
- Rooftop Solar Phase II installations, which are not covered under PM Surya Ghar.
- Group housing society connections claiming the common-facility rate, unless dedicated to common facilities only. That capacity ceiling also counts plants residents already installed.
GERC Notification No. 5/2016 adds a floor and a ceiling: not less than 1 kW, not more than 1 MW. After its First Amendment (Notification No. 2 of 2017), residential consumers were freed from the 50% of sanctioned load cap that still binds other categories. Our discom glossary entry defines the licensee terms.
Gujarat discoms: who serves which area
Use the licensee named on your electricity bill. The table below is a guide to the usual regional split, drawn from GUVNL’s company profile and public references. Boundaries at city edges differ by source (Gandhinagar and Bharuch are two examples), so the bill, not the table, decides.
| Licensee | Region | Typical areas (verify on your bill) |
|---|---|---|
| UGVCL | North Gujarat | Mehsana, Banaskantha, Patan, Sabarkantha, Aravalli and parts of Gandhinagar district |
| MGVCL | Central Gujarat | Vadodara, Anand, Kheda, Panchmahal, Dahod, Mahisagar, Chhota Udaipur |
| PGVCL | Saurashtra and Kutch | Rajkot, Jamnagar, Bhavnagar, Junagadh, Kutch, Porbandar, Amreli, Surendranagar, Morbi |
| DGVCL | South Gujarat | Surat district outside the city licence area, Bharuch, Navsari, Valsad, Tapi, Narmada, Dang |
| Torrent Power | Private licensee | Ahmedabad and Gandhinagar city areas and an area of Surat city |
The steps are the same for every licensee, but the contact points differ:
- UGVCL, MGVCL, PGVCL, DGVCL. Register on the National Portal, choose the discom from the portal list, and pick a vendor registered with it. The discom does the physical inspection and net metering under the GERC rules.
- Torrent Power. The portal application still starts on the National Portal, but inspection, the net meter and the connectivity agreement are Torrent’s. Ask the vendor which Torrent office handles your area before the design is frozen.
- All licensees. Ask for written confirmation of the inspection date, the meter type and who submits completion documents. Do not assume that another licensee’s timeline applies to yours.
We have not published per-discom turnaround figures. Earlier versions of Gujarat guides quoted fixed day counts per discom, but we found no published discom data to support them, so this guide uses the stage durations prescribed in the GERC regulations (table below) instead.
How to apply through the portal and your discom
The route has two halves: a national application and a state-level connection process. Do them in order.
- Register on the National Portal for PM Surya Ghar with your consumer number and the licensee named on your electricity bill.
- Select a vendor registered or empanelled with that discom. The portal publishes the list.
- Have the vendor survey the site and propose a capacity that fits your roof and your consumption.
- Complete the net metering agreement, now part of the portal application, per PIB (2026).
- Install, then have the discom carry out its physical inspection.
- Upload documents, let the e-token activate, then redeem it in your portal profile.
MNRE has also removed three friction points, according to PIB and MNRE (2026). The technical feasibility requirement is waived. Automatic load increase up to 10 kW is allowed. And a collateral-free bank loan at repo rate plus 50 basis points, presently 5.75% per annum over 10 years, is available. Our status check guide explains how to read each stage.
Why the registered vendor requirement matters
This is not a formality, and the obligations attach to the vendor rather than to you. MNRE Office Memorandum F. No. 318/6/2022-GCRT dated 10 June 2022 requires vendors installing residential rooftop solar to register or empanel with the beneficiary’s discom. Know these conditions before you pay a deposit.
| Requirement | Detail, per MNRE (2022) |
|---|---|
| Performance bank guarantee | ₹2,50,000, valid at least five years |
| Empanelment validity | One year initially, renewed annually |
| Discom list publication | On the discom website, updated every month |
| Maintenance obligation | Comprehensive maintenance for at least five years |
| Technical manpower | At least three trained technical staff declared |
| Penalty for misleading information | Blacklisting and forfeiture of the guarantee |
Vendor discipline is active, not theoretical. MNRE deactivated 66 registered PM Surya Ghar vendors for a month over backlogs of pending applications, as reported by SaurEnergy (2026). It also advised vendors not to hold applications beyond 60 days without valid reason. A deactivated vendor disappears from the consumer selection page. Check your vendor’s live status before signing, using our vendor verification guide.
Documents and timeline, stage by stage
The GERC 2016 regulations prescribe a duration per activity rather than one headline number. These are regulatory targets, not observed averages, and PM Surya Ghar has since removed some steps.
| Stage | Prescribed duration, per GERC (2016) | Key documents |
|---|---|---|
| GEDA registration certificate | 5 days from a complete application | Application, consumer details |
| Chief Electrical Inspector approval | 10 days | Single line diagram, earthing diagram, wiring diagram |
| Discom letter for feasibility report | 5 days | Proof of legal possession of roof, co-owner NOC, CEI approval, load details |
| Field technical feasibility report | 10 days from the head office letter | Feeder and transformer data, no dues certificate, no pending dispute certificate |
| In-principle consent after the report | 5 days | Connectivity charge demand, or a strengthening estimate |
| Connectivity agreement | Within 15 days of consent, or 30 days if strengthening is needed | Signed agreement, charges paid |
| Project completion window | 6 months from the letter | Installation records |
| Completion documents | 5 days from the intimation letter | Ownership proof, CEI charging approval, meter and CTPT test certificates, IEC test reports for modules, inverter, cables, junction box and meter |
| Meter installation | 7 days | Solar meter plus bidirectional meter |
| GEDA commissioning certificate | 5 days from intimation | Joint site visit |
Two timings sit outside that table. Central assistance is processed within 15 days of approval, per MNRE (2024). The installer undertakes operation and maintenance for five years after commissioning, according to the SURYA Gujarat portal (GUVNL, 2026).
Connectivity charges are fixed by system size, per GERC (2016). They are ₹1,500 from 1 kW up to 6 kW, ₹10,000 above 6 kW up to 100 kW, and ₹50,000 above 100 kW up to 1 MW. Our documents checklist covers the national side.
Net metering and settlement under the GERC order
For residential consumers, GERC Notification No. 5/2016 dated 18 June 2016 works like this. If the discom supplies more than your system generates in a billing period, you are invoiced for net consumption at your prevailing tariff. If injection exceeds consumption, the discom buys the excess at the Average Pooled Power Purchase Cost (APPC) set by the Commission for your commissioning year. That rate then holds for the 25-year system life.
Three features are easy to miss:
- Banking runs for one billing cycle only. There is no open-ended annual carry-forward in the 2016 text.
- Generation is set off against units consumed, not against load or demand. Fixed and demand charges remain payable.
- Your commissioning year fixes your export rate for 25 years. Commission a year later and you inherit a different APPC.
The Gujarat Solar Power Policy 2021 set the residential and MSME surplus rate at ₹2.25 per unit, as reported by SaurEnergy (2020), and removed the 50% sanctioned load ceiling. The framework is moving again. GERC has published draft Grid Interactive Distributed Renewable Energy Sources Regulations, 2026 to replace the 2016 regulations. The draft adds net billing, group net metering and virtual net metering, and a public hearing was held on 18 June 2026, as reported by SaurEnergy (2026). Until it is notified, confirm your commissioning-year rate with your licensee. Our net metering guide and the APPC glossary entry explain the mechanics.
Worked example: a 3 kW residential budget
This is labelled arithmetic on published benchmark figures. It is not a quotation and not a market price.
Assumptions. A 3 kW residential system in Gujarat. Standard, non-special-category rates. MNRE benchmark cost of ₹50,000 per kW for the first 2 kW and ₹45,000 for the additional kW, with effect from 13 February 2024, per MNRE (2024). GERC connectivity charge for a 1 to 6 kW system. No state top-up, because no current Gujarat order could be verified.
| Line item | Calculation | Amount |
|---|---|---|
| MNRE benchmark cost, first 2 kW | ₹50,000 x 2 | ₹1,00,000 |
| MNRE benchmark cost, third kW | ₹45,000 x 1 | ₹45,000 |
| Benchmark subtotal | ₹1,45,000 | |
| Discom connectivity charge | 1 to 6 kW slab | ₹1,500 |
| Gross reference outlay | ₹1,46,500 | |
| Central assistance, first 2 kW | ₹30,000 x 2 | ₹60,000 |
| Central assistance, third kW | ₹18,000 x 1 | ₹18,000 |
| Total central assistance | ₹78,000 | |
| Verified Gujarat state top-up | No current order located | ₹0 |
| Reference outlay after assistance | ₹1,46,500 less ₹78,000 | ₹68,500 |
Central assistance covers ₹78,000 of a ₹1,45,000 benchmark, about 53.8%. Quotations differ from the benchmark in both directions, and assistance is paid on installed capacity, not on what you spent. MNRE publishes its own examples on the same basis: 1.5 kW yields ₹45,000 and 2.5 kW yields ₹69,000, per MNRE (2024). Size to your consumption first, using our string sizing calculator once you have module and on-grid inverter candidates.
What to put in a Gujarat solar quote
An installer should show the gross project cost separately from any assistance. A projected subsidy is not cash received, and payback depends on your actual bill, roof and export treatment. Ask for these items in writing:
| Item | Evidence to request |
|---|---|
| Central PM Surya Ghar assistance | Amount and status shown in your own portal application |
| Gujarat state top-up, if claimed | The current government or discom order, who is eligible, the claim channel and funding status |
| Full system cost | Itemised modules, inverter, structure, cables and protection, meter work, labour and tax |
| Modules | Exact model numbers and DCR status. MNRE’s ALMM page lists modules and cells, not inverters |
| Inverter | Exact model, datasheet and the grid and safety documents your discom asks for |
| Export credit | The GERC billing terms for your commissioning year |
Keep any unverified state benefit out of the base case. For a roof-specific generation estimate, use the solar quotation checklist and the irradiance guide.
Why Gujarat applications get rejected or stall
Most refusals are documentary or technical. Very few are discretionary.
- Transformer headroom. Cumulative rooftop capacity at one distribution transformer cannot exceed 65% of its peak capacity, per GERC (2016). If the feeder is full, you wait or pay for augmentation.
- Non-DCR modules. Their use in any form makes the installation ineligible, per MNRE (2024). Ask for module make, model and DCR status in writing.
- Missing CEI approval. The single line, earthing and wiring diagrams need Chief Electrical Inspector sign-off first.
- No dues or pending dispute. The feasibility checklist requires both certificates, per GERC (2016).
- Missed document deadlines. Completion documents filed later than 5 days after the intimation lead to cancellation and forfeiture of charges paid, per GERC (2016).
- Project overrun. After the 6 month window, a 2 month notice is issued; silence then means cancellation within 30 days.
- Bank account mismatch. Proof that the account is held by the consumer is required before release, per MNRE (2024).
- Vendor status. A deactivated vendor cannot accept new applications, as reported by SaurEnergy (2026).
Nobody can promise you an outcome or a particular slab, and rules vary by discom. Our rejection reasons guide walks through the appeal path.
What Surya Gujarat does not cover
This is the section most sales conversations skip. Every point comes from the published regulations.
The discom carries no responsibility for your subsidy. The net metering interconnection agreement is explicit, per GERC Notification No. 5/2016. The distribution licensee shall not be liable for delivery or realisation by the consumer of any fiscal or other incentive provided by the central or state government.
Network costs are yours. The consumer bears all setup costs including metering and interconnection, per GERC (2016). That extends to modifications, service line upgrades and transformer upgrades where required. Strengthening work takes 45 days after you pay the estimate.
Your bill does not go to nothing. Generation is set off against units, not load or demand, so fixed and demand charges still appear. The scheme does not promise a zero electricity bill.
The state top-up figure circulating online is dated. A GEDA subsidy of ₹10,000 per kW of installed PV, capped at ₹20,000 per consumer, was reported by PV Tech (2016). It was released after commissioning, against an initial target of 100,000 consumers. That is a 2016 report, not evidence of a 2026 entitlement, and no current GEDA order restating it could be located.
The state portal’s own rates are old. Its discovered rates page is labelled 2020-21, weak ground for arguing a 2026 quotation down.
On our own scope: Qbits manufactures solar inverters and does not install, so we cannot file your application. For an on-grid system, see our on-grid inverter range and its datasheets for the documents your discom asks for. To find installers and service partners near you, use the Qbits partner directory and then verify each one on the National Portal as described in our vendor guide.
Solar subsidy in Gujarat: is there a last date?
There are three different “dates” people mix up, and they have different answers.
| What you mean | What is published | Source |
|---|---|---|
| Central PM Surya Ghar scheme end | Implementation period runs to 31 March 2027 | MNRE guidelines, clause 2(d) |
| A deadline for your own application | No household-level cut-off is stated in the guidelines | MNRE guidelines |
| SURYA Gujarat state window | Last new-application window shown: 23 November 2023 to 8 December 2023 | SURYA Gujarat portal (GUVNL) |
As of October 2026 we found no official notice extending PM Surya Ghar beyond 31 March 2027, and none ending it earlier. That does not make waiting safe. Assistance is released only after your system is installed, inspected by the discom and approved on the portal, so a project started close to the end date can miss the window if inspection slips. Work backwards from the end of March 2027, allow for your discom’s queue, and ask the vendor in writing what happens to the contract if the application is not approved in time.
Any “last date” shown in a social post, WhatsApp forward or sales pitch should be checked against the National Portal and your discom before you pay a deposit.
The Bottom Line
Surya Gujarat gave the state an early lead and a working single-window portal. The money in 2026 comes from PM Surya Ghar, and any state layer must arrive through the National Portal with an order behind it.
Three things to do next:
- Read your bill, not a district map. Identify your licensee (UGVCL, MGVCL, PGVCL, DGVCL or Torrent Power) and apply against that name on the National Portal.
- Get the top-up in writing or leave it out. Ask your discom or GEDA for the current state-benefit order, and exclude any unverified top-up from your net cost.
- Document the inverter side before you commit. Talk to our team via contact us for the datasheets and compliance documents your discom asks for at inspection.
Sources checked 24 September 2026 and re-checked 14 October 2026 (state top-up status, scheme end date, loan terms, discom areas): MNRE Order No. 318/17/2024-Grid Connected Rooftop (16 March 2024); MNRE OM F. No. 318/6/2022-GCRT (10 June 2022); GERC Notification No. 5/2016 (18 June 2016) with Notification No. 2 of 2017; MNRE state-wise installed renewable capacity as on 31 August 2026; PIB and MNRE (25 March 2026); SURYA Gujarat portal, GUVNL; JMK Research (2026); PV Tech (2016); SaurEnergy (2020, 2026); MNRE operational guidelines for residential CFA (clauses 2(d), 5, 6, 7), as read on 14 October 2026; PIB release of March 2026 for loan terms; GUVNL company profile for discom areas. The National Portal and PIB pages returned access errors on 14 October 2026, so figures from them are taken from the MNRE guideline text and from news summaries of PIB releases. Rules change and vary by discom, so verify with your own licensee first.
Qbits inverters for this guide
Specs below come from each model's datasheet. Confirm the exact model and current written terms with Qbits before you buy.
QB 1.5/2.0/2.7/3.0/3.3/3.6/4.0KTLS
- Power
- 1.5–4 kW
- Phase
- Single-phase
- MPPT
- Single-MPPT
QB 4.2/4.6/5/5.4/6KTLS
- Power
- 4.2–6 kW
- Phase
- Single-phase
- MPPT
- Single-MPPT
QB 5/6/8/10/12/15/17KTLC
- Power
- 5–17 kW
- Phase
- Three-phase
- MPPT
- Dual-MPPT
Frequently Asked Questions
Is the Surya Gujarat scheme still open for new applications in 2026?
How much subsidy does a 3 kW rooftop system get in Gujarat?
Does a Gujarat state top-up stack on PM Surya Ghar, and is the old ₹10,000 per kW GEDA figure still valid?
Which discom handles rooftop solar in Gujarat?
What rate does Gujarat pay for surplus rooftop solar exported to the grid?
Do I have to use an empanelled or registered vendor?
Why do Gujarat rooftop solar applications get rejected?
How long does the whole process take in Gujarat?
Akash Hirapara CFO, Qbits Energy
CFO overseeing solar financing, procurement, and channel partner enablement at Qbits.